Collgar Windfarm
Project Owner - International Investment Bank UBS and the Retail Employees Superannuation Trust (REST)
Client - Catcon
Location - Merredin Wheatbelt Region of Western Australia
Quantity of Concrete Delivered - 40,000
Project Duration - August 2010 to March 2011
Details - MCS provided mobile batch plant operations, quality concrete supply, mix design services and project testing for all aspects of this $750m renewable energy project.
MCS's contribution involved quality concrete supply for the foundations of the 111 2.0MW wind turbines. MCS was proud to be a part of a project of this nature, with the project saving up to 700,000 tonnes of CO2 emissions to meet Western Australia's power requirements.
This project was also for a repeat client, a testament that MCS continues to meet both client and project deliverables.